From 3 Weeks Behind to 3 Weeks Ahead

Project Review

Frameworks was hired by a large commercial contractor in the Atlanta market to frame a clubhouse for a major national builder. Our scope included framing with our own roof trusses and wall panels, installing house wrap, windows, and exterior doors.


The Challenge

Before we arrived, weather delays had already put the project three weeks behind schedule. The project manager left for vacation the day after we started framing.


The Result

We completed the framing within four business days, and by the time the PM returned, the entire clubhouse had been framed, wrapped, and fitted with windows and doors, pushing the timeline a full three weeks ahead.


• Fast, efficient install
• Clean job site with minimal waste
• Perfect nailing pattern on sheathing
• Builder now quoting 5 additional projects

The Takeaways

“This is the cleanest job site I’ve had. The speed, the panels, the precision—it all made a difference. I want Frameworks on every job I do from now on.”

– Builder Project Manager